Block Capacity Dashboard

The Final Block Sizes for the 2023-2024 Program Year, including the Addition of Uncontracted Capacity Allocation from the 2022-2023 Program Year, in MW, are:

CEJA CategoryGroupCategoryTier (Public Schools only)Size kW (Public Schools only)2026-27 Program Year block prior to uncontracted capacity reallocation (MW)2026-27 block + reallocated uncontracted 2025-26 capacity2025-26 Program Year waitlist (MW)2026-27 Program Year opening available capacity (MW)
Small DGN/ADG180.00236.710.00236.71
Large DGN/ADG180.00236.710.00236.71
TCSA (30%)CS78.00119.5216.00103.52
TCSB (70%)CS182.00241.540.00241.54
CDCSA (30%)CS15.0019.250.0019.25
CDCSB (70%)CS35.0053.408.4844.92
EECA (30%)CS (75%)49.5055.880.0055.88
DG (25%)16.5018.630.0018.63
B (70%)CS (75%)115.50130.390.00130.39
DG (25%)38.5043.460.0043.46
Public SchoolsN/ACS (25%)Tier 1, 2, and EJC (70%)<250 kW (25%)4.816.670.006.67
250 – 1000 (50%)9.6313.3513.35
1000-5000 (25%)4.816.676.67
Tier 3, 4 (30%)<250 kW (25%)2.062.862.86
250 – 1000 (50%)4.135.725.72
1000-5000 (25%)2.062.862.86
DG (75%)Tier 1, 2, and EJC (70%)<250 kW (25%)14.4420.020.0020.02
250 – 1000 50%)28.8840.0440.04
1000-5000 (25%)14.4420.0220.02
Tier 3, 4 (30%)<250 kW (25%)6.198.588.58
250 – 1000 (50%)12.3717.1517.15
1000-5000 (25%)6.188.578.57

Detailed Program Data

[1] Allocated Capacity: Refers to the amount of capacity made up by batched applications that have been officially awarded program capacity and have been ICC approved.

[2] Batched Capacity: Refers to the amount of capacity made up by submitted applications that have been batched and the batch fee has been paid or is pending payment.

[3] Submitted Capacity: Refers to the amount of capacity made up by submitted applications which have not yet been batched by the Approved Vendor.

[4] Available Capacity: Refers to the capacity remaining after deducting allocated, batched, and submitted capacity from the 2022-2023 Program Year block size.

Waitlists from 2023-24 Program Year:

Waitlists from 2021-22 Program Year: