Traditional Community Solar (TCS) Scoring Update

Preliminary scores for all TCS projects submitted during the “first day” application window on June 3, 2024 will be shared individually with each AV today, July 19, 2024. AVs should expect an email directing them to the TCS scoring file located in their AV SharePoint folder, which commences the scoring cure period. Please see the initial, planned scoring schedule below.  

  • Application Review Period: Applications undergo initial review by Program Administrator – Approximately 4 weeks (Complete) 
  • Application Cure Period: Approved Vendors cure deficiencies identified by Program Administrator – Approximately 2 weeks (Complete) 
  • Application Scoring Period: Program Administrator begins scoring process for all relevant applications (those submitted without deficiencies and those that successfully cure deficiencies during the 2-week cure period) – Approximately 3 weeks (Complete) 
  • Scoring Cure Period: AVs are offered a chance to review initial score and dispute and resolve any discrepancies – Approximately 2 weeks (currently July 19 – August 2) 
  • Scores published: AVs wishing to appeal their project score will have two weeks from the receipt of scores to submit an appeal to the Program Administrator  
  • Random selection event to ordinally rank projects with tied scores  
  • Final scores and project selection published