Large DG applications (including EEC and Public Schools) must include Proof of Interconnection as evidence of an agreement with the utility for future interconnection, or proof that interconnection has already taken place.Proof of Interconnection must show the interconnection address, through but not limited to:
- An Interconnection Agreement signed by both the interconnection customer and the interconnecting utility prior to the date of Part I application submittal (batch submission).
- Utility portal screenshot displaying interconnection approval, utility name, project address, project size, and approval expiration date.
- If a project is already energized prior to application, a Certificate of Completion of Interconnection will be accepted in lieu of an executed Interconnection Agreement or proof of interconnection approval.