All Part I Large DG applications (including EEC and Public Schools) must include Proof of Interconnection Approval as evidence of an agreement with the utility for future interconnection, or proof that interconnection has already taken place. Proof of Interconnection Approval must show the interconnection address. Acceptable documentation is as follows:
- Interconnection Agreement signed by both the interconnection customer and the interconnecting utility prior to the date of Part I application submittal.
- Utility Portal screenshot displaying interconnection approval, utility name, project address, project size, and approval expiration date.
- If a project is already energized prior to application, a Certificate of Completion of Interconnection will be accepted in lieu of an executed Interconnection Agreement or Proof of Interconnection Approval.
- Statement from the utility acknowledging an interconnection application is not needed, and they are aware of the installation.